Executive Summary
This paper will explore the issue of project
management and planning style based on the Aceh experience for
its implications here in Yogyakarta. Through examining case
studies from UN-HABITAT, Canadian Red Cross and UPC-UPLINK, the
paper will emphasise the significant role of the participatory
approach in the rebuilding processes. We will further show how
the modern, commercial contracting model, or ordinary project
management style does not efficient enough in managing the
massif rebuilding practices.
Three pressing questions that relate to
successful project management (PM) will frame this paper:
-
What lessons can we transfer from one
relief project in one context to one in a very different
context?
-
To what extent does the local, traditional
culture and the culture of the aid organization influence
project delivery?
-
In what ways can PM skills and techniques
be better developed to cope with these complex contexts?
Some challenges are common across relief
projects and this paper will attempt to categorize these lessons
into generic classes, with a second order categorization to
better describe their impact, likely magnitude, and suggested
ways of addressing these issues.
Background
The tsunami and earthquake disaster that
struck Aceh on 26 December 2004 resulted in an influx of over
350 aid organizations – only some of which had experience in the
relief and reconstruction business. Three years after the
disaster, the housing reconstruction remains less than half
finished with only 45,000 houses completed from 120,000
committed.
Where are the blockages in the housing
delivery system? Is it the government or the housing provider?
The answer is both. Many NGO’s active in Aceh were originally
humanitarian organizations without any pertinent experience in
housing reconstruction. Lured by huge donations, hundreds of
NGOs jumped into the reconstruction process without any
supporting background, knowledge and experience in post-disaster
housing reconstruction and rehabilitation. Now after three
years, these compounded disasters are becoming glaringly
obvious.
Previously, organizations that work in
disaster relief and post conflict reconstruction focused on
non-housing sectors. Housing is always classified as internal
government business, whereas donors and NGOs are more interested
in reconstructing schools, clinics, micro-infrastructure, or
other structures classified as non-private entitlement, since
its easier to identify, justify and does not require a lengthy
and potentially conflict-laden process of beneficiary selection,
verification and validation.
In Aceh the only organizations specialized in
rebuilding houses are UN-HABITAT, CHF, and Habitat for Humanity.
The rest were NGOs involved in watsan, child welfare and
protection, and livelihoods regeneration (e.g., Save The
Children, OXFAM), who dared to take the plunge into housing –
but without any clear objectives and previous experience.
Others, like the International Federation of the Red Cross,
with all its experience in emergency response has not shown any
significant progress on their housing project. Even the World
Bank, as the number one leading agency in the development
sector, has shown little expertise, not much training, poorly
integrated experience in its organizational culture and learning
cycle with the end result being significant delays in the MDF
(Multi Donor Fund) housing project. The result has been big
blockages in housing delivery for the disaster survivors. These
complications are compounded by fraud indications as well as
quality assurance in the housing projects.
The challenge for these well-funded
organizations is how to transfer knowledge between international
staff and locally hired professionals, which obviously did not
take place easily. This is an important lesson for many
international organizations with diverse experiences in
different fields and different parts of the world. Apparently,
money alone cannot buy good teams.
When a massive scale disaster like that in
Aceh happens, lack of expertise in planning, building,
designing, and project management becomes obvious. As a result,
donors and NGOs simplify the problems by applying a technocratic
approach, drawing on hard core engineers, who mainly emphasize
the anti-seismic, construction qualities with no adequate
understanding of the socio-cultural aspect. Simplifying the
process as a construction output leads to major shortfalls in
the activities.
This lack of knowledge in post-disaster
planning and project management needs to be addressed, given so
many disasters happen in Indonesia. This paper will explore 3
housing projects in Aceh and observe 1) how each were
implemented, 2) identify the bottlenecks, and 3) the shortfalls
and prominent variables that determined project success.
We will show that there is quite significant
evidence to prove how a participatory approach to project
management style is most successful. We will then outline an
alternative approach to project management in post-disaster
areas.
Community Based Reconstruction: myth or
applicable solution?
In Aceh, the meaning of community
participation downgraded rapidly, in essence becoming
meaningless but essentially used jargon much as “sustainable
development” or “gender mainstreaming”. Such phrases are
compulsory terms to secure funds. Yet they are rarely
accompanied by adequate understanding. Moreover, many NGOs in
Aceh claim to use participatory approaches, but only
participation in its lowest form (see table 1).
Table 1: level of
participation and empowerment

The
concept “participatory” has drawn debate concerning what is
participatory and what is not, especially surrounding issues of
defining what active involvement, never mind empowerment, means
in project design, materialization and supervision.
In Aceh specifically, “participation” was
even more likely to fail for a number of factors. The most
prominent of these was the conflict, the damaged social fabric,
a dysfunctional governmental and educational infrastructure, the
lack of trust, and the resulting closed-minded society.
On the other hand, the weaknesses of NGOs in
Aceh were due to their narrow approach to rehabilitation and
reconstruction from the physical aspect without looking at the
accumulated effects of post-trauma from either conflict or
disaster. This was compounded with a misunderstanding of why
the people of Aceh failed to empower themselves.
Only a handful of NGOs were truly able to
implement a community-based approach, whereas most proved they
did not really understand the concept by producing
reconstruction projects without empowering its beneficiaries.
The tendency to treat to housing reconstruction as nothing more
than housing projects.
Methodology
A 3rd party monitoring system run
by University of Syiah Kuala (UNSYAH) was set up to review all
reconstruction projects. It uses 3 key indicators to benchmark
the success of each project. The indicators are 1). Construction
Quality, 2). Satisfactory Index, and 3). Accountability index.
Those 3 indicators will be used to appraise
UN-HABITAT, Canadian Red Cross and UPC-UPLINK in their Housing
Provider Performance and subsequently triangulated with direct
site visits. The goal of this paper is to show, then, how the
participatory approach is significant in the rebuilding
processes and is, in fact, a major determining factor leading to
the success or failure of the project.
Table 2: Monitoring
Results
|
Organization |
Accountability Index |
Satisfactory Index |
Construction Quality Index |
|
UPLINK (Urban Poverty Linkage) |
Very High |
Very High |
Very High |
|
CRC (Canadian Red Cross) |
Low |
Low |
High |
|
UN-HABITAT (United Nation Human Settlement) |
High |
High |
High |
Source: UN-HABITAT
– UNSYIAH 3rd Party Monitoring Result
The UNSYIAH survey (sponsored by UN-HABITAT)
comprises Focus Group Discussion with a clustered group of
beneficiaries and local leaders, and technical analysis to
review construction quality. The Accountability Index and
Satisfaction Index is based on the beneficiaries’ opinion of
their benefactor, whereas the Construction Quality is measured
through direct on-site observation with a building inspector,
architect and civil engineers, that refer and comply to the Aceh
Building Code standard.
-
The survey concluded that UPLINK has
delivered the highest possible output in Construction Quality,
Beneficiaries Satisfaction and Accountability Index
-
Meanwhile, CRC delivered high quality
houses but they scored low in satisfaction and accountability.
This shows how construction quality is not the main factor
that drives the satisfaction index.
-
UN-HABITAT
comes out with slightly lower performance compared to
UPLINK. Nevertheless, UN-HABITAT was able to deliver high
quality construction with high satisfaction accountability
marks.
Why were these three projects different from
each other? What factors determined UPLINK’s very high marks as
opposed to CRC’s low? Why can CRC deliver a high quality output
in term of construction, yet fail to influence gain satisfaction
and accountability? Finally, why was UN-HABITAT, the most
experienced of the 3 in housing reconstruction, not able to
match the UPLINK performance?
The answer, according to
UNSYAH’s monitoring surveys, is that satisfaction depends on
both the end product (i.e., the house) and the participatory
process that creates a sense of ownership toward the building
process.
Project Case Studies
In this section we will compare methods and
approaches that have been used by 3 different organizations in
Aceh. UPLINK, Urban Poverty Linkage, is a left-leaning, grass
roots organization with much experience in community organizing,
but no pertinent experience in housing reconstruction. Second is
CRC, Canadian Red Cross Movement, an aid agency that specializes
in emergency response, but lacks experience in housing
reconstruction Third is UN-HABITAT, the United Nation Human
Settlement Program, strongly bureaucratic, but fully experienced
in reconstruction, and balanced between their capitalist
ideologies and a community participation approach.
Table 3: Project
size to location
|
Organization |
Scale of Project |
Project Status |
Location |
|
UPLINK (Urban Poverty Linkage) |
Medium Size (3123 units) |
Finished and Handed over |
Aceh Besar |
|
CRC (Canadian Red Cross) |
Large Size (6676 units) |
Early stage in the constriction Processes |
Aceh Besar, Aceh Jaya, Nias |
|
UN-HABITAT (United Nation Human Settlement) |
Medium Size (4104 units) |
Closing Down Stage |
Banda Aceh, Aceh Besar, Pidie, Nias, Simeleu |
Source: UN-HABITAT
– UNSYIAH 3rd Party Monitoring Result
Facing Complicating Factors: Location
-
UPLINK successfully focused on one
particular area in a district that still had adequate
macro-infrastructure. This is the most prominent variable that
determined UPLINK’s performance in expediting their housing
construction progress. The clear focus enabled UPLINK to
establish more efficient management chains, reduce the
coordination blockages and stimulate multi-sectoral approach
decisively, which influenced people’s perceptions toward the
processes and project output.
-
CRC, with a huge program and huge budget,
began with the challenge to select project location for such a
large program. The easiest locations for work, the more
developed east coast, were already occupied by medium or small
Aid Agencies, leaving lots of gaps to be filled in the more
devastated west coast areas. CRC had to accept these locations
for the BRR approval, with half of their project allocated on
Aceh Jaya, the most devastated areas in Aceh, plus small
numbers in Aceh Besar and Nias Island. Nias alone became one
big bottleneck with disputes and double claims between the CRC
and UN-HABITAT, as well as other implementing agencies. This
competition influencing the housing delivery system indicates
that many agencies are competing with each other to fulfil
their commitments to their donors. Nias as a remote island
created major logistical issues, with the bulk of building
materials needing to be transported from Sumatra Utara, 12-20
hours by sea. This mobilization doubled the cost more so than
the mobilization and sluggishness issues CRC encountered in
Aceh Jaya. CRC was accused of lacking project management
skill, experience, compounded by an organizational culture
that was not suited to the massive project. In their own
defence, CRC put the blame on the BRR and the Local Government
since there were no supports for infrastructure or land
titling.
-
UN-HABITAT operated in a small scale in
Nias and Simeleu island and put most of their energy towards
the easiest part located on Banda Aceh, Aceh Besar and Pidie.
Housing distribution numbers needed to be carefully arranged
during early phase of the project implementation plan. Where
the organization had to operate in remote areas (e.g. Nias and
Simeleu), they made sure that the committed number was as low
as possible, fully recognizing the inadequate logistical
support.
Lessons Learnt: Location
Focusing on one or two districts is important
to ascertain project success. Coordination, multi-sector,
cross-cutting issues can be easily resolved if the management
span is reduced. The more scattered the project areas, the more
coordination is required. By working in a comfort zone where
basic infrastructure is available will always provide
significant leverage toward project success. Avoiding operating
in a massive scale in areas where infrastructure support is
lacking became a major decisive strategy toward project success.
Managing the project size has a direct
correlation to project speed. By keeping the number of
committed houses on the medium threshold, organizations were are
to be more flexible and adaptive in the approach they took.
UPLINK and UN-HABITAT simply managed a controllable committed
number of houses and carefully expedited their project delivery
enabling them to put more focus toward construction quality
issues.
Facing Complicating Factors: Participation
Rebuilding approach and level of community
participation became the second most significant factor
determining quality of project. The “rebuilding approach” means
the project orientation, management style, delegation of
management load. It is this factor embraced by UN-HABITAT and
UPLINK that will be compared to CRC’s approach. CRC
sub-contracted their construction to commercial contractors, a
far too common model that has been proven to fail in Aceh and
Nias.
Table 4: Level of
Participation
|
Organization |
Rebuilding Approach |
Community Involvement (see table 1) |
Role of Facilitator in the rebuilding process |
Housing Design / Village Spatial Planning |
|
UPLINK (Urban Poverty Linkage) |
Participatory Approach; community managed funds in the
rebuilding processes |
Fully Participate (Empowered) |
High |
Design by the community, facilitated by Uplink technical
staff |
|
CRC (Canadian Red Cross) |
Contractual based with Big Contractors approach |
Fully Consulted |
Low |
Top down approach, community consulted |
|
UN-HABITAT (United Nation Human Settlement) |
Participatory Approach; the community managing the fund in
the rebuilding processes |
Fully Participate (Collaborated) |
High |
Design by the community, facilitated by UN-HABITAT technical
staff |
Source: UN-HABITAT
– UNSYIAH 3rd Party Monitoring Result
1. UPLINK’s Community Based Housing
Reconstruction Program used a fully participatory approach in
collaboration with a sister organization that they themselves
founded for this purpose. The JUB (Jaringan Udep Beusare) was a
new entity in Aceh to enforce local involvement based on a
leftist, pro-poor spirit. Together with JUB (who were also
beneficiary community members), UPLINK commenced their
activities by facilitating community workshops, fully
consulting, collaborating and empowering the community to manage
their own housing program. UPLINK brought the community together
to develop a Village Spatial Plan for their own village, and
used Community Action Planning methodology for the housing
design, which involved all the stakeholders including women and
minority groups as active participants. The design workshop
creates a bridge between the community perspective and
appropriate technical specifications, specifically for
anti-seismic construction. Moreover, UPLINK applies a
co-operative management style that enables and encourages the
community to fully participate during the project implementation
cycle.
The Community Cluster Model
The communities are grouped into clusters of
5 households. Each cluster elects their representative and
leader. Each cluster opens a cluster savings account, to receive
the bulk fund for the cluster. These funds are disbursed in 3
trances, based on the construction materialization progress.
In the preparation phase, UPLINK’s social
facilitator engages the community to work as a group and to
co-operate to strengthen togetherness and community spirit. This
step efficiently addresses the fragmentation caused by a long
conflict compounded further by the disaster. The training,
always held in local vernacular, includes demonstration,
brainstorming in design principle, building material selection,
construction practice, and water & sanitation.
In the implementation phase, the technical
facilitator provided advice to those building their house as
well as those who worked with builders. This step insured
acceptable anti-seismic constriction quality.
This “Community Contract” model is based on a
belief that a well-organized community is a legal entity,
eligible to be awarded a contract to deliver their own
properties. This community contract model also reduced the
internal management load by dividing each project into
self-managed clusters that reinforced the community’s resilience
and management skill, increased their sense of belonging, and at
the same time, ensured accountability and transparency in each
phase of the construction. The method relied on social controls
that were the responsibility of each cluster member to monitor
fellow members. Where a household did not deliver the product
according to the contract timing or quality specifications,
tranche payments to the cluster were withheld until all members
caught up. The social control model enhanced construction
quality since all cluster members contributed, looked after, and
supervised one another. No ‘every man for himself’ applied
anymore, and the power of control was decentralized to the
grass-roots level decisively.
2. CRC implemented their program using a
common commercial contractual model; though to some extent it
blended well with public consultation during the decision-making
processes. The community was fully consulted in beneficiary
selection (verification and validation), village spatial
planing, and in housing design phases. But CRC lacked real
engagement and empowerment. CRC believed that a massive housing
reconstruction could be rapidly performed through national and
multi-national construction firms. These profit-oriented
companies fully realized that profit margins would not be
significant enough in comparison to operational costs. The
result was lack of interest from qualified companies for the CRC
project in Aceh Jaya, where infrastructure and logistic support
remain poorly served. Further, this approach does not bridge
community needs with a profit-oriented company tied to a
contractual - deliverable output - framework.
Further compounding the issue, problems
within the community needed to be resolved through active
facilitation processes that create common understandings and
trust between stakeholders. This basic ingredient is not common
to a modern construction company, clearly inexperienced in
dealing with such a complex project. CRC has encounter basic
common mistake by abandoning community entitlement to
participate and engaged as a holistic approach. Even with
engineers and an experienced Project Manager on staff, CRC could
not cope with the complexity of coordinating such a vast
rebuilding project with the needs of a severely damaged
community. This exposes CRC’s lack of experience. They wrongly
simplified the housing issue as a construction project and lost
track completely of the context of community during the process,
taking real participation, engagement and facilitation
as an obstruction in project operation.
3. The final example, UN-HABITAT applied a
similar model to UPLINK, but allocated much lower cost per
house. Overall the UN-HABITAT and UPLINK model is the same, a
slight discrepancy in the participatory level, whereas UPLINK
implements a fully leftist and socialist empowerment model, and
in UN-HABITAT is fully collaborate with the community and
prevent to apply any ideological approach.
Lessons Learned
-
Following a massive disaster such as that
in Aceh and Nias, a high participatory model
will enable the community to engage and participate actively,
gave more flexibility throughout the program implementation
cycle, expedite the knowledge transfer process through
hands-on training,
at the same time, to increase peer monitoring amongst housing
cluster members. The Community Contract model decentralized
the project management burden by transferring responsibility
to the community as implementers, as collective supervisors,
as well as risk and responsibility takers. Our case studies
showed that a well-facilitated community contract model will
lead to far more successful outcomes than the common
commercial contractual model.
-
In the CRC case, it is important to keep
the program as simple as possible both in size and expected
outputs, and to work with local implementing agencies, not
through a Commercial Contractual model. A centralized system
to procure bulk building materials by big suppliers and
contractors did not significantly assist performance in Aceh,
since infrastructure is a major problem. Our studies show the
best applicable solution is to lessen pressure on project
management by decentralizing the program into smaller, simpler
and manageable units, applied through a collaborative approach
in conjunction with local NGOs who fully understand the local
landscape, or with a fully participatory community contract
model.
-
Providing broad flexibility during the
project implementation cycle is the key to success in
participatory projects. Flexible, adaptive, responsive and
transparent are basic keywords to underpin the process. Hence,
facilitation is the tool that links all of the indicators and
variables. Facilitation in the rebuilding process firmly
contributed to capacity building, ensuring the community was
well organized, and was a vigorous catalyst in behaviour
change. The facilitation process further allowed the
implementing agency to identify, address, and resolve
potential threats, disputes, and conflict, by steering the
community to reach a common understanding and to determine
priorities.
Other Complicating Factors: Land Titles
Other
independent factors played a significant role in administering
an adaptive approach on housing reconstruction projects in Aceh.
Table 5 describes certain indicators which influenced project
outcomes.
Table 5: Additional
Factors
|
Organization |
Land Titling and Building Permit |
National Staff |
Enabling Early Return |
Integrated Development |
|
UPLINK (Urban Poverty Linkage) |
Promote Community Land Adjudication |
Managing fully with Indonesian staff |
Yes, with a barrack |
Yes, supporting the community with Livelihood Package:
agriculture, revolving fund mechanism, others |
|
CRC (Canadian Red Cross) |
Not willing to build unless the plot is already
certified by BPN |
Fully expatriate |
Yes, with transitional shelter |
Yes, supporting with livelihood and watsan packages |
|
UN-HABITAT (United Nation Human Settlement) |
Promote Community Land Adjudication |
Collaborative, expatriate and Indonesian Staff |
No |
No |
Source:
UN-HABITAT – UNSYIAH 3rd Party Monitoring Result |
-
UPLINK ignored the centralized system
administered by National Land Authority (BPN), who required
housing providers to comply with BPN procedures.
Meanwhile, UPLINK used a community land adjudication process
to resolve land-titling issues. UPLINK believed the
entitlement process could be addressed easily through
community land mapping and staking as a strategy to reach
agreement on what would later lead to the issuance of legal
certificates from the GoI. This approach was indeed very
effective and land disputes have not arisen. This highly
participatory land mapping process, accompanied by high tech
surveying equipment, was successfully tried after the Gujarat
earthquake and thus the experienced team was able to perform
quickly and efficiently. This response – although risky –
allowed UPLINK to move forward without waiting for legal
instruction and contributed to UPLINK’s speedy recovery.
-
Unlike UPLINK, land titling became a major
problem for CRC. Most of their sites in Aceh Jaya encountered
land ownership problems. This complexity was worsened by CRC’s
rigid approach to resolve the land issue before commencing
groundbreaking activities. It is common for international
agencies to comply with GoI regulations in order to prevent
potential conflict, but this decision backfired on the Agency.
What was expected by the Red Cross Movement in Aceh was to
solicit land certificates before starting to build. To some
extent, it should save the organization from legal charges,
but this decision delayed project mobilization.
-
UN-HABITAT has substantial previous
experience resolving land issues (relocation, resettlement and
land acquisition). UN-HABITAT supported a community land
adjudication system, from which arose only a few minor cases
in Lamsenia Village in Aceh Besar, where relocation could not
be avoided. To resolve that, UN-HABITAT worked with JRS
(Jesuit Relief Service) and Yayasan Puter to use a
participatory Land Relocation system. In collaboration with
the community, they identified new sites owned by community
members. The agreement stipulated an entitlement to buy the
land collectively from the landlord, with the landlord
providing two years grace period to the community before
repayment to commence. No collateral loans were required. This
was a “gentlemen’s agreement” based on broad community
consensus as a result of a successfully managed participatory
approach.
Local Staff
The role of a good local team is essential
for their understanding of local political and social
landscapes. It’s easier for them to bridge the language barrier
in ways that can affect the decision-making processes, and thus,
ways of thinking.
1.
UPLINK established their firm management system in a way
that ensured an egalitarian relationship between benefactor and
beneficiaries, which was highly appreciated and successfully
reduced the gaps between the two of them.
2.
With CRC, all of the senior and decision-making posts
were occupied by expatriates. The gap between them and the
locals created major problems for internal management with local
staff only being used as a tool to achieved project outputs.
Thus, they failed to capture the local perspective, with
unpredictable and undetectable results.
3.
UN-HABITAT management included a well blended combination
of local and international staff, with most of the expatriates
having pertinent experience in the housing sector, most having
more than 10 years in Indonesia, most speaking Indonesian fairly
fluently, and understanding Indonesian culture, although not
particularly Acehnese culture. This mix between local and
expatriate that understood the cultural, social and political
landscapes enabled UN-HABITAT to function more flexibly.
Quick Return
-
Enabling an early
return for survivors to TLC (Temporary Living Centre) or TS
(Temporary Shelter) is the indicator of success. Yet
verification and validation processes are major obstacles.
Firstly, survivors are dispersed. Secondly, the manipulative
approach in managing beneficiaries leads to. Lastly, is lack
of a data management system to indicate the distribution and
number of survivors at the earliest phase.
-
UPLINK mobilized
the community to return to their place of origin early. By
enabling an early return, the process of identifying the
eligible beneficiaries and their entitlements, as well as land
titling, was easier and prevented dispute possibilities.
Firmly screening the beneficiaries’ entitlements prevented
irresponsible people from claiming false entitlements to
housing assistance.
Early return then firmly supported active community
involvement in decision making processes and led to less of an
individualistic mind set.
-
UN-HABITAT has no
expertise in emergency phase rebuilding. Thus they did not
enable early return, this is for some extend draw some
difficulties in organizing the community on the early phase.
-
CRC did enable early return to their origin
which resolved the beneficiaries’ issue easily.
Multi-sectoral Approach
A multi-sectoral approach can underpin the
Local Economic Development by supporting local women and men to
actively revitalize their livelihood activities.
1.
UPLINK provided the beneficiaries with small grants that
enabled them to gain access to capital for income generating
activities. Several JUB members received a pedicap. In addition
UPLINK assisted the community to produce a sustainable building
material workshop
(or Community Builder’s Yard) such as environmentally
pressed clay brick (clay with cement and pressed by hand). These
bricks reduced the use of timber and was more environmentally
friendly since the brick does not need to be fired. UPLINK also
established a new mushroom plantation which already has overseas
orders and will provide a new income source for the community.
The integration of housing with livelihoods has provided the
community with adequate support to revive their capacity as well
as promoting best practice in linking reconstruction with the
next level of the development stage.
2.
CRC also aimed to provide the community with an
integrated development plan, micro-infrastructure as well as
livelihood and income-generating provisions. Unfortunately since
there was no significant movement towards the housing delivery,
especially in Aceh Jaya, the full process is stuck, waiting for
housing as the foremost component to be delivered first.
3. UN-HABITAT
clearly avoided integrated development issues, but UN-HABITAT
actively engaged the BRR micro infrastructure department to
provide basic infrastructure within their working areas, a smart
move from the limited resource organization. With integrated
development issues, as a specialized UN Agency, UN-HABITAT does
not provide livelihood support. But this lacking was remedied
with a collaborative and co-operative approach. Differing from
UPLINK, which tends to reject NGO involvement in their working
areas,
UN-HABITAT applies a fully co-operative approach and coordinates
other agencies in other sectors, such as education,
child-protection, watsan, capacity building and so on. With this
co-operative approach UN-HABITAT is able to create a driving
force toward the multi-sector approach, delivered through
different organizations, while at the same time promoting a
collaborative approach between different stakeholder.
Lessons Learned
-
Complying with government policy is a basic
rule for international agencies. Unfortunately given to
complications in Indonesian land administration systems, rigid
compliance will not help the housing provider to expedite the
program. Applying community land adjudication as an
alternative solution proved to significantly expedite the
housing reconstruction phase delivered by UPLINK and
UN-HABITAT. Community land adjudication promotes agreements
between stakeholders, between neighbours to endorse private
land entitlement, secures land occupancy.
-
Enabling Early Return helps the community
to be organized effectively and efficiently if it is
accompanied with well prepared basic life support
infrastructure. Organizing the community during the early
phases is much easier than one or two months later. This
“momentum window” effectively helped a fragile community to
channel its perception, understanding and attitude towards a
more constructive, democratised, and civilized mutual-support
system.
-
Although CRC was able to relocate most of
the IDPs (Internally Displaced People) to newly built
Temporary Shelters, the lack of infrastructure provision or
integration with livelihood support reduced the early return
momentum to the lowest level.
-
Delivering a comprehensive program through
involvement and participation of other organizations where
specific expertise is lacking is a must, as long as it is not
doubling or competing. There is no special formula to address
this coordination issues, It all depends on the willingness to
co-operate between each agency.
Conclusions
What Determines Project Speed?
Talking about speed is talking about delay.
Delays have been caused by several reasons: shortage of able
human resources, logistical problems, bureaucratic and
institutional problems, and difficulties in coordinating the
multitudes of organizations. Basically there have been the
following types of delays:
-
Delay in decision making caused by inexperience,
hesitation, hysteria and lack of leadership.
-
Delay caused by weakness in implementation structure
and/or approach, caused among other things by long negotiation
between GOI and donor agencies and long debate about appropriate
approach and team works among (internal) implementing
organizations.
-
Delay in procurement (delay in designing or specifying
details, or caused by shortage of materials and manpower,
aggravated also by bad access to certain remote areas)
-
Delay in the process of trust building and consequential
late agreements between homeowners and providing organizations.
By now,
participatory and fast-tracking techniques are widely known.
Homeowner’s participation in the experience of UN-Habitat,
UPLINK and others has proven to speed up reconstruction, because
they not only feel mobilised (from sedentary living in the
barracks or temporary shelters) but also develop a sense of
belonging. Elizabeth Haussler of Build Change said that
homeowner’s involvement is the key to quality and satisfaction,
and should be the target in improving building practices.
The WB was said to have detailed 56 steps
in housing reconstruction, of which many are not critical and so
can be fast-tracked if properly analysed. The main delays were
caused wrong or delayed decisions.
The main cause of delay in UN-Habitat’s
experience is an indecisive, confusing phase that many other
organizations also experienced. Organizations try to simulate
and formulate answers for over-anticipated problems before they
had the confidence to start. This was made worse by formalizing
the anxiety into an instruction to wait for guidelines. Many
large formal organizations were naturally also inhibited by
their system of accountability.
Community-Based Reconstruction
as an Alternative approach
UN-Habitat’s seminar on lessons-learned in
Yogyakarta on 29th August 2007[14]
concluded that community-based reconstruction is not unrealistic
at all and has indeed proven to be faster and resulting in
highest quality and satisfaction, as shown by the Universitas
Syah Kuala (UNSYAH) survey. The highest scoring clusters of
houses were organised by UPLINK with multi-layers of community
participation. There is a consensus that community-based housing
reconstruction can respond quickly to urgent needs and thus can
achieve relief at an earlier stage; mobilize solidarity among
the members of a community, and therefore build social capital;
allow for better gender equity; strengthen local institutions;
achieve good planning leading to high quality results; limit
disaster vulnerability; and can be done with good monitoring to
achieve transparent accountability. Aceh has proven that
Community-Based Development (CBD) can be done on a large scale.
Community-based reconstruction also resulted in better targeting
of beneficiaries.
More needs to be said to counter the
attractiveness of the “contractor” approach now even further
pursued by BRR, as it is said to reduce risk, intensity of
transaction, and staff involvement on the provider’s side. While
these points are indeed true, other goals that need to be
achieved in the reconstruction process, such as building social
capital, cannot be achieved with the “contractor approach.”
Doubts about community-based approaches come
from lack of understanding, experience and knowledge about how
to organise it, fear of chaos, a shortage of professionals well
trained in its implementation, and fear that it will take too
long for a post-disaster situation.
A
possibility worth exploring is to combine the contractor
approach with community participation. Communities or homeowners
could manage the contracting themselves, or to authorise payment
to contractors. Here community participation is seen as a part
of a process that can be applied in different stages and ways.
It runs the risk of being superficial but nevertheless would be
useful in building up sense of belonging and quality control.
There is a need for a standard of what is
meant by participation and community based approach. There are
reports about situations where community-based approach clusters
are surrounded by non community-based approaches, resulting in
confusion among beneficiaries. Community-based approach also
requires a fair lead-time, even though this is compensated by
the speed and satisfaction in the later stage. Most failures in
community approach are caused by the delay in its start up,
leaving little time for the participatory process. In some cases
there is a genuine shortage of capacity to conduct
community-based approach, despite genuine good intention to
satisfy community’s aspiration. The shortage of community
facilitators is serious.
We must also be realistic about both the
pluses and minuses in the process of community-driven
development. The lesson learned is that community-based
reconstruction is not all rosy and smooth. Not all communities
are as romantically communal as we hope. Although communities
are not “ideal”, it is however proven that negative prejudices
are not all true either in Aceh. Facilitators need to be trained
in that respect. They need to be able to respond to unexpected
varying demands, and capable to coordinate various clusters of
resources. Community-based approach requires that government
make policies to support and regulate and encourage it.
Community-based does not mean leaving the governments behind.
A minimum standard of community participation
is viable. There are references that can be used and adapted.
Level of participation (from mobilisation to decision making)
can be determined by referring, for example, to Sherry
Arnstein’s ladder. Participation can also be specified for
different aspects and stages and/or aspects of reconstruction
process: organization, planning of houses and village and
settlements and cities, procurement, construction, evaluation,
etc. A matrix could be developed for this purpose of combining
levels of participation and specific participatory activities in
each stage and aspects of reconstruction.
UN-Habitat’s practices, and UPLINK’s highly
participatory practices at all levels, are among the resources
that should be looked into to formulate the minimum standard of
community-based practices.
The above are important ingredients for
successful community participation program in post-disaster
reconstruction. Drawing from the lessons of Aceh and Nias,
there is an urgent need to quickly enhance the capacity of the
beneficiaries to rebuild their homes without having to wait for
the government to deliver on the reconstruction of houses.
Empowerment through housing development can be implemented by
communities without depending upon the government. It is all
our hopes that a rapid program could be executed in post
disaster areas so that the problems and failures that we faced
in Aceh will not be repeated.